205 Augusta Ave is in Kensington-Chinatown. It's outside TRCA flood hazard areas and there are 7 planning applications nearby (three approved, two waiting for a hearing date, one under review, one other).

Data as of Nov 8, 2026 · Every item lists its source

Follow this address
Key findings
  • Outside TRCA flood hazard areas.
  • 7 planning applications within 250 m: three approved, two waiting for a hearing date, one under review, one other.
Building permits1in the last 5 years
Applications nearby7active, within 250 m
Flood hazardOutsideTRCA mapping
Next collectionNov 10garbage, green bin and yard waste
Bathurst StDundas StSpadina AveLeonard AveOxford StNassau StWales AveAugusta AveDenison AveDenison SqKensington AveBaldwin StHickory StCasimir StBellevue AveHuron StSt Andrew StD'Arcy StLarch St1234567Map data: City of Toronto (Toronto Centreline)Dundas StSpadina AveOxford StWales AveAugusta AveDenison AveDenison SqKensington AveBaldwin StHickory StNassau StBellevue AveSt Andrew St1234567Map data: City of Toronto (Toronto Centreline)
The red dot is 205 Augusta Ave. The circle shows 250 metres, about a 3-minute walk. Numbers match the applications in “What’s changing nearby”.

03The building

ItemFindingPrecisionSource
Building orders and noticesNone on recordThis addressBuilding Construction/Demolition Violations
Building permits, last 5 years1 permitThis addressBuilding Permits · 2 on record

1 building permit in the last 5 years. For comparison, about 1 in 10 Toronto addresses had any permit in that time. Permits show work the City approved; they don't show work done without a permit.

Short-term rentalNot registeredThis addressShort Term Rentals Registration
Heritage statusNot on the Heritage RegisterThis addressHeritage Register

It isn't listed or designated on the City's Heritage Register.

Permit history: 2 projects from 2 permits
  • Change of Use · inspection · issued Jul 21, 2026
    Proposal to change use from office to wellness centre at second floor only.New scope for second floor is event space, Group A2 occupancy (M.I) · Permit 26 153530
  • Interior renovation and plumbing · completed Apr 4, 2025
    Plumbing - Interior alterations to ground and 2nd floor of on residential building. Ground floor to be used as studio/office space and 2nd floor as office space. · Permit 11 135987

04Risks and environment

ItemFindingPrecisionSource
River flood hazardOutsideThis addressTRCA Regulation mapping 2025
Lake shoreline hazardOutsideThis addressTRCA Regulation mapping 2025
TRCA regulated areaOutsideThis addressTRCA Regulation mapping 2025

TRCA's maps show this address is outside the areas that could flood from rivers in a major storm (TRCA plans for a storm like Hurricane Hazel in 1954) and outside lake shoreline hazards. Basement flooding from overloaded sewers can still happen anywhere in the city.

Lead in tap-water tests, postal area M5T0% of tests above Ontario's limitYour area · M5TNon Regulated Lead Sample · 85 tests, Feb 20, 2014 to Sep 11, 2026

In postal area M5T, 0 of 85 home tap-water samples (0%) tested above Ontario's limit for lead (10 micrograms per litre). Across Toronto, 2.0% of samples did, so M5T is lower than the city overall. Health Canada recommends a stricter limit of 5 micrograms per litre: 1 samples here (1.2%) were above it. These are voluntary tests, mostly from older homes, so they don't tell you about this house. Lead comes from old pipes and plumbing, not the City's treatment plants. If your home was built before the mid-1950s, you can get a free test kit by calling 311.

TRCA mapping is for screening, not site-specific decisions. Lead results are voluntary samples from homes in the postal area, not this address.

01What’s changing nearby

7 active planning applications within 250 m (about a 3-minute walk): three approved, two waiting for a hearing date, one under review, one other. That's more than at most Toronto addresses (the typical address has 1).

  1. 1
    309 Augusta Ave · 131 m away
    Official Plan / Rezoning: a request to change the Official Plan or zoning so something new can be built

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed six storey hotel with restaurant components containing 2194sqm of non-residential gross floor area. No parking is proposed.
    File 26 206718 STE 11 OZ · submitted Jul 22, 2026 · City record
  2. 2
    33 Kensington Ave · 141 m away
    Committee of Adjustment · Consent (severance): permission to split a lot or change property lines

    The hearing was postponed. A new date hasn't been published yet.

    Section 57(1) of the Planning Act allows the assignment of authority to the Secretary-Treasurer, Committee of Adjustment or his/her designate to approve a Validation of Title.
    File B0039/20TEY · submitted Jun 1, 2020
  3. 3
    230 Augusta Ave · 146 m away
    Committee of Adjustment · Minor variance: permission to bend a zoning rule, such as height, size or setbacks

    The hearing was postponed. A new date hasn't been published yet.

    File A0508/25TEY · submitted Jun 30, 2025
  4. 4
    610 Dundas St W · 176 m away
    Committee of Adjustment · Minor variance: permission to bend a zoning rule, such as height, size or setbacks

    The hearing was postponed. A new date hasn't been published yet.

    To legalize and to maintain a rear three-storey addition, that was constructed without an authorized building permit. Also, to permit one residential dwelling unit within the rear portion of the ground level (behind a non-residential…
    File A0657/25TEY · submitted Jun 26, 2025
  5. 5
    353 College St · 213 m away
    Site Plan: City review of the design and layout of a new building

    City planners approved the site plan, with conditions to meet before a building permit.

    Proposal for site plan approval related to a five storey addition to existing hostel with portion of ground floor to be used as retail
    File 18 111118 STE 20 SA · submitted Jan 29, 2018 · City record
  6. 6
    355 College St · 217 m away
    Site Plan: City review of the design and layout of a new building

    City planners approved the site plan, with conditions to meet before a building permit.

    Proposal for site plan approval related to a five storey addition to existing hostel with portion of ground floor to be used as retail
    File 18 111118 STE 20 SA · submitted Jan 29, 2018 · City record
  7. 7
    357 College St · 221 m away
    Site Plan: City review of the design and layout of a new building

    City planners approved the site plan, with conditions to meet before a building permit.

    Proposal for site plan approval related to a five storey addition to existing hostel with portion of ground floor to be used as retail
    File 18 111118 STE 20 SA · submitted Jan 29, 2018 · City record
Short-term rentals nearby26 registered homesWithin 250 mShort Term Rentals Registration

26 homes within 250 m are registered with the City as short-term rentals (stays of less than 28 days, like Airbnb). That's more than at almost all Toronto addresses.

Development Applications; Committee of Adjustment Applications; Short Term Rentals Registration.

02City services

ItemFindingPrecisionSource
Garbage and recyclingTuesdaysThis addressSolid Waste Collection Schedule

Next: November 10: garbage, green bin and yard waste. November 17: recycling and green bin. Green bin goes out every week; garbage and recycling alternate.

City councillorDianne SaxeWard 11Councillor_Saxe@toronto.ca · 416-392-4009

05Quick answers about 205 Augusta Ave

Is 205 Augusta Ave in a flood plain?

No. TRCA maps it outside river flood and lake shoreline hazard areas. Basement flooding from sewers can still happen anywhere. Source: TRCA Regulation mapping 2025.

What is being built near 205 Augusta Ave?

There are 7 active planning applications within 250 metres (three approved, two waiting for a hearing date, one under review, one other). The closest is at 309 Augusta Ave, 131 m away. Source: Development Applications; Committee of Adjustment Applications.

Has 205 Augusta Ave been renovated?

Yes. The City has 2 building permits on record, 1 in the last 5 years. Source: Building Permits.

Is 205 Augusta Ave a heritage property?

No. It isn't listed or designated on the City's Heritage Register. Source: Heritage Register.

When is garbage day at 205 Augusta Ave?

Collection is on Tuesdays. Green bin goes out every week; garbage and recycling alternate weeks. The next garbage pickup is Nov 10, 2026. Source: Solid Waste Collection Schedule.

Answers are generated from the data on this page and update when the data changes.

06From the archives

Kensington Avenue looking north from St. Andrew
1980 · 89 m awayKensington Avenue looking north from St. AndrewCity of Toronto Archives, Fonds 200, Series 1465, File 53, Item 2
181 Baldwin St
1919 · 113 m away181 Baldwin StCity of Toronto Archives, Fonds 200, Series 372, Subseries 58, Item 835
181 Baldwin St
1919 · 113 m away181 Baldwin StCity of Toronto Archives, Fonds 200, Series 372, Subseries 58, Item 834
North west corner of Augusta Avenue and Nassau Street
1932 · 154 m awayNorth west corner of Augusta Avenue and Nassau StreetCity of Toronto Archives, Fonds 200, Series 372, Subseries 66, Item 39
Nassau St., looking south east across Augusta Ave., Toronto, Ont.
1978 · 154 m awayNassau St., looking south east across Augusta Ave., Toronto, Ont. Courtesy of Toronto Public Library
North west corner of Augusta Avenue and Nassau Street
1932 · 154 m awayNorth west corner of Augusta Avenue and Nassau StreetCity of Toronto Archives, Fonds 200, Series 372, Subseries 66, Item 38
334 Spadina Avenue, Welina Hawkins, Reginald [Beyaut]
1942 · 218 m away334 Spadina Avenue, Welina Hawkins, Reginald [Beyaut]City of Toronto Archives, Fonds 1266, Item 82631
334 Spadina Avenue, gun
1942 · 218 m away334 Spadina Avenue, gunCity of Toronto Archives, Fonds 1266, Item 82634
334 Spadina Avenue, Welina Hawkins, Percy [Absett]
1942 · 218 m away334 Spadina Avenue, Welina Hawkins, Percy [Absett]City of Toronto Archives, Fonds 1266, Item 82633

Photo locations are matched from each photo’s title against City street and address data, so some may be off. Report a wrong location

205 Augusta Ave, Toronto M5T: permits, flood risk and what's planned nearby · My Address in Toronto