251 Queen St E is in Moss Park. It's outside TRCA flood hazard areas and there are 17 planning applications nearby (11 under review, four approved by the tribunal, one hearing on Nov 4, one other).

Data as of Nov 8, 2026 · Every item lists its source

Follow this address
Key findings
  • Outside TRCA flood hazard areas.
  • 17 planning applications within 250 m: 11 under review, four approved by the tribunal, one hearing on Nov 4, one other.
Building permits0in the last 5 years
Applications nearby17active, within 250 m
Flood hazardOutsideTRCA mapping
Next collectionNov 11recycling and green bin
Jarvis StQueen StShuter StRichmond StSherbourne StParliament StAdelaide StGeorge StTrefann StPower StBerkeley StOntario StSeaton St123456789101112Map data: City of Toronto (Toronto Centreline)Shuter StQueen StRichmond StSherbourne StAdelaide StBritain StOntario StPrincess StBerkeley St123456789101112Map data: City of Toronto (Toronto Centreline)
The red dot is 251 Queen St E. The circle shows 250 metres, about a 3-minute walk. Numbers match the applications in “What’s changing nearby”.

03The building

ItemFindingPrecisionSource
Building orders and noticesNone open (1 closed)This addressBuilding Construction/Demolition Violations
Building permits, last 5 years0 permitsThis addressBuilding Permits · 0 on record

The City has no building permits on record for this address. About 9 in 10 Toronto addresses also had none in the last 5 years.

Short-term rentalNot registeredThis addressShort Term Rentals Registration
Heritage statusNot on the Heritage RegisterThis addressHeritage Register

It isn't listed or designated on the City's Heritage Register.

04Risks and the ground

ItemFindingPrecisionSource
River flood hazardOutsideThis addressTRCA Regulation mapping 2025
Lake shoreline hazardOutsideThis addressTRCA Regulation mapping 2025
TRCA regulated areaOutsideThis addressTRCA Regulation mapping 2025

TRCA's maps show this address is outside the areas that could flood from rivers in a major storm (TRCA plans for a storm like Hurricane Hazel in 1954) and outside lake shoreline hazards. Basement flooding from overloaded sewers can still happen anywhere in the city.

Lead in tap-water tests, postal area M5A3.0% of tests above Ontario's limitYour area · M5ANon Regulated Lead Sample · 134 tests, May 21, 2014 to Oct 15, 2026

In postal area M5A, 4 of 134 home tap-water samples (3.0%) tested above Ontario's limit for lead (10 micrograms per litre). Across Toronto, 2.0% of samples did, so M5A is about the same as the city overall. Health Canada recommends a stricter limit of 5 micrograms per litre: 9 samples here (6.7%) were above it. These are voluntary tests, mostly from older homes, so they don't tell you about this house. Lead comes from old pipes and plumbing, not the City's treatment plants. If your home was built before the mid-1950s, you can get a free test kit by calling 311.

TRCA mapping is for screening, not site-specific decisions. Lead results are voluntary samples from homes in the postal area, not this address.

01What’s changing nearby

17 active planning applications within 250 m (about a 3-minute walk): 11 under review, four approved by the tribunal, one hearing on Nov 4, one other. That's more than at 9 in 10 Toronto addresses.

Nov
4
Nearby · 112 mCommittee of Adjustment hearing: 90 Ontario StTBA · Committee of Adjustment · Consent (severance) · File B0056/26TEY
  1. 1
    90 Ontario St · 112 m away
    Committee of Adjustment · Consent (severance): permission to split a lot or change property lines

    A public hearing is set for Nov 4, 2027 at TBA. Neighbours can send comments or speak at the hearing.

    To obtain consent to sever the property into two lots (Building B and Building C) and to create new reciprocal stratified easements/rights-of-way.
    File B0056/26TEY · submitted Sep 23, 2026
  2. 2
    191 Sherbourne St · 139 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Site Plan application to permit two tall buildings (39- and 40-storeys), containing 693 new residential dwelling units, 525 square metres of non-residential space, and a new public park.
    File 24 254630 STE 13 SA · submitted Dec 30, 2024 · City record
  3. 3
    201 Sherbourne St · 187 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Site Plan application to permit two tall buildings (39- and 40-storeys), containing 693 new residential dwelling units, 525 square metres of non-residential space, and a new public park.
    File 24 254630 STE 13 SA · submitted Dec 30, 2024 · City record
  4. 4
    285 Shuter St · 207 m away
    Committee of Adjustment · Minor variance: permission to bend a zoning rule, such as height, size or setbacks

    The hearing was postponed. A new date hasn't been published yet.

    File A0445/26TEY · submitted May 22, 2026
  5. 5
    150 Sherbourne St · 215 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Site Plan Control application for a 7,544.3 square metres City of Toronto community centre to replace the existing John Innes Community Centre.
    File 24 106375 STE 13 SA · submitted Jan 19, 2024 · City record
  6. 6
    150 Sherbourne St · 215 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed underground transit station for the Ontario Line at Moss Park.
    File 23 124235 STE 13 SA · submitted Mar 17, 2023 · City record
  7. 7
    261 Queen St E · 218 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Site Plan Approval for a 25-storey mixed-use building having a non-residential gross floor area of 24,936 square metres, and a residential gross floor area of 35,803 square metres. A total of 446 residential dwelling units, and 180…
    File 21 169132 STE 13 SA · submitted Jun 11, 2021 · City record
  8. 8
    301 Queen St E · 220 m away
    Official Plan / Rezoning: a request to change the Official Plan or zoning so something new can be built

    The Ontario Land Tribunal (formerly the OMB) approved it.

    Proposal for a new 19-storey mixed-use building next to the existing Berkeley Church, containing 150 dwelling units and 1,066 square metres of non-residential gross floor area.
    File 16 161250 STE 28 OZ · submitted May 25, 2016 · City record
  9. 9
    301 Queen St E · 220 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    INACTIVE Site Plan application for a 25-storey mixed-use building: 206 dwelling units, 6 levels of below-grade parking, total combined GFA 15,711 sq. m.
    File 16 161258 STE 28 SA · submitted May 25, 2016
  10. 10
    305 Queen St E · 227 m away
    Official Plan / Rezoning: a request to change the Official Plan or zoning so something new can be built

    The Ontario Land Tribunal (formerly the OMB) approved it.

    Proposal for a new 19-storey mixed-use building next to the existing Berkeley Church, containing 150 dwelling units and 1,066 square metres of non-residential gross floor area.
    File 16 161250 STE 28 OZ · submitted May 25, 2016 · City record
  11. 11
    305 Queen St E · 227 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    INACTIVE Site Plan application for a 25-storey mixed-use building: 206 dwelling units, 6 levels of below-grade parking, total combined GFA 15,711 sq. m.
    File 16 161258 STE 28 SA · submitted May 25, 2016
  12. 12
    311 Queen St E · 229 m away
    Official Plan / Rezoning: a request to change the Official Plan or zoning so something new can be built

    The Ontario Land Tribunal (formerly the OMB) approved it.

    Proposal for a new 19-storey mixed-use building next to the existing Berkeley Church, containing 150 dwelling units and 1,066 square metres of non-residential gross floor area.
    File 16 161250 STE 28 OZ · submitted May 25, 2016 · City record
Short-term rentals nearby8 registered homesWithin 250 mShort Term Rentals Registration

8 homes within 250 m are registered with the City as short-term rentals (stays of less than 28 days, like Airbnb). That's more than at most Toronto addresses (the typical address has 2).

Development Applications; Committee of Adjustment Applications; Short Term Rentals Registration.

02City services

ItemFindingPrecisionSource
Garbage and recyclingWednesdaysThis addressSolid Waste Collection Schedule

Next: November 11: recycling and green bin. November 18: garbage, green bin and yard waste. Green bin goes out every week; garbage and recycling alternate.

City councillorChris MoiseWard 13Councillor_Moise@toronto.ca · 416-392-7903

05Quick answers about 251 Queen St E

Is 251 Queen St E in a flood plain?

No. TRCA maps it outside river flood and lake shoreline hazard areas. Basement flooding from sewers can still happen anywhere. Source: TRCA Regulation mapping 2025.

What is being built near 251 Queen St E?

There are 17 active planning applications within 250 metres (11 under review, four approved by the tribunal, one hearing on Nov 4, one other). The closest is at 90 Ontario St, 112 m away. Source: Development Applications; Committee of Adjustment Applications.

Is 251 Queen St E a heritage property?

No. It isn't listed or designated on the City's Heritage Register. Source: Heritage Register.

When is garbage day at 251 Queen St E?

Collection is on Wednesdays. Green bin goes out every week; garbage and recycling alternate weeks. The next garbage pickup is Nov 18, 2026. Source: Solid Waste Collection Schedule.

Answers are generated from the data on this page and update when the data changes.

06From the archives

Ridout, Samuel, 'Roselands', Seaton St., w. side, n. of Queen St. E.
1860 · 55 m awayRidout, Samuel, 'Roselands', Seaton St., w. side, n. of Queen St. E. Courtesy of Toronto Public Library
Ridout, Samuel, 'Roselands', Seaton St., w. side, n. of Queen St. E.
1800 · 55 m awayRidout, Samuel, 'Roselands', Seaton St., w. side, n. of Queen St. E. Courtesy of Toronto Public Library
Window display of antique shop on Queen St E, south side, west of Sherbourne
1981 · 82 m awayWindow display of antique shop on Queen St E, south side, west of SherbourneCity of Toronto Archives, Fonds 1526, File 68, Item 61
Window display of antique shop on Queen St E, south side, west of Sherbourne
1981 · 82 m awayWindow display of antique shop on Queen St E, south side, west of SherbourneCity of Toronto Archives, Fonds 1526, File 68, Item 62
Corner of Sherbourne St. and Queen St., looking north-west
1972 · 82 m awayCorner of Sherbourne St. and Queen St., looking north-westCity of Toronto Archives, Fonds 2032, Series 841, File 50, Item 21
Queen St. E., looking east from Sherbourne St., Toronto, Ont.
1910 · 82 m awayQueen St. E., looking east from Sherbourne St., Toronto, Ont. Courtesy of Toronto Public Library
Queen St E., north side, east of Sherbourne
1977 · 82 m awayQueen St E., north side, east of SherbourneCity of Toronto Archives, Fonds 1526, File 68, Item 64
View of Queen Street East at Sherbourne Street
1981 · 82 m awayView of Queen Street East at Sherbourne StreetCity of Toronto Archives, Fonds 1526, File 75, Item 9
Corner of Sherbourne St. north of Queen St., looking west
1972 · 82 m awayCorner of Sherbourne St. north of Queen St., looking westCity of Toronto Archives, Fonds 2032, Series 841, File 50, Item 20