835 Yonge St is in Rosedale-Moore Park, on the City's Heritage Register. It's outside TRCA flood hazard areas and there are 7 planning applications nearby (five approved, two approved by the tribunal).

Data as of Nov 8, 2026 · Every item lists its source

Follow this address
Key findings
  • It is individually designated under the Ontario Heritage Act (Part IV).
  • Outside TRCA flood hazard areas.
  • 7 planning applications within 250 m: five approved, two approved by the tribunal.
Building permits1in the last 5 years
Applications nearby7active, within 250 m
Flood hazardOutsideTRCA mapping
Next collectionNov 11recycling and green bin
Bay StBelmont StDavenport RdRosedale Valley RdPark RdYonge StChurch StAylmer AveMcMurrich StScollard StMc Alpine StFrichot AveRosedale RdPine Hill RdCollier StAsquith AveYorkville AveReynolds St1234567Map data: City of Toronto (Toronto Centreline)Bay StYonge StChurch StPark RdAylmer AveMcMurrich StSevern StRosedale RdCollier StAsquith AveYorkville AveScollard St1234567Map data: City of Toronto (Toronto Centreline)
The red dot is 835 Yonge St. The circle shows 250 metres, about a 3-minute walk. Numbers match the applications in “What’s changing nearby”.

03The building

ItemFindingPrecisionSource
Building orders and noticesNone on recordThis addressBuilding Construction/Demolition Violations
Building permits, last 5 years1 permitThis addressBuilding Permits · 1 on record

1 building permit in the last 5 years. For comparison, about 1 in 10 Toronto addresses had any permit in that time. Permits show work the City approved; they don't show work done without a permit.

Short-term rentalNot registeredThis addressShort Term Rentals Registration
Heritage statusPart IVThis addressHeritage Register

It is individually designated under the Ontario Heritage Act (Part IV). Changes to its heritage features need a heritage permit from the City.

Permit history: 1 project from 1 permit
  • Sign Building Permit Related · permit issued · issued Jul 9, 2026
    Total of 6 first party signs on various elevations, all on the first storey, displaying static copy.***PETRO CANADA***Overhanging Stucture SignsSign 1(1a) 1.82m L x 1.94m W x 0.42m D x 6.15m H above… · Permit 26 178419

04Risks and environment

ItemFindingPrecisionSource
River flood hazardOutsideThis addressTRCA Regulation mapping 2025
Lake shoreline hazardOutsideThis addressTRCA Regulation mapping 2025
TRCA regulated areaOutsideThis addressTRCA Regulation mapping 2025

TRCA's maps show this address is outside the areas that could flood from rivers in a major storm (TRCA plans for a storm like Hurricane Hazel in 1954) and outside lake shoreline hazards. Basement flooding from overloaded sewers can still happen anywhere in the city.

Lead in tap-water tests, postal area M4W1.2% of tests above Ontario's limitYour area · M4WNon Regulated Lead Sample · 82 tests, Apr 27, 2014 to Mar 17, 2026

In postal area M4W, 1 of 82 home tap-water samples (1.2%) tested above Ontario's limit for lead (10 micrograms per litre). Across Toronto, 2.0% of samples did, so M4W is lower than the city overall. Health Canada recommends a stricter limit of 5 micrograms per litre: 5 samples here (6.1%) were above it. These are voluntary tests, mostly from older homes, so they don't tell you about this house. Lead comes from old pipes and plumbing, not the City's treatment plants. If your home was built before the mid-1950s, you can get a free test kit by calling 311.

TRCA mapping is for screening, not site-specific decisions. Lead results are voluntary samples from homes in the postal area, not this address.

01What’s changing nearby

7 active planning applications within 250 m (about a 3-minute walk): five approved, two approved by the tribunal. That's more than at most Toronto addresses (the typical address has 1).

  1. 1
    874 Yonge St · 81 m away
    Committee of Adjustment · Minor variance: permission to bend a zoning rule, such as height, size or setbacks

    The Committee of Adjustment approved it on Nov 22, 2023.

    To alter the redevelopment plan for a mixed-use building approved under Site Specific By-law 697-2021(OLT) by permitting an increase in the building height, an increase in the total gross floor area, and the elimination of visitor parking…
    File A0612/23TEY · submitted Jul 10, 2023
  2. 2
    36 Yorkville Ave · 177 m away
    Site Plan: City review of the design and layout of a new building

    City planners approved the site plan, with conditions to meet before a building permit.

    Site Plan Amendment application to further amend the previously approved Site Plan Amendment application for the site (File No. 18 203283 STE 27 SA) to permit a raised terrace and canopy at the southwest corner of the existing building…
    File 23 220948 STE 11 SA · submitted Oct 31, 2023 · City record
  3. 3
    820 Church St · 183 m away
    Committee of Adjustment · Minor variance: permission to bend a zoning rule, such as height, size or setbacks

    The Committee of Adjustment approved it on Sep 18, 2024.

    To alter the development standards for a 38-storey hotel building (as approved under Site Specific Zoning By-law 300-2023) by increasing the non-residential gross floor area, building height, and mechanical penthouse height. The new…
    File A0616/24TEY · submitted Jul 9, 2024
  4. 4
    906 Yonge St · 200 m away
    Official Plan / Rezoning: a request to change the Official Plan or zoning so something new can be built

    The Ontario Land Tribunal (formerly the OMB) approved it.

    Zoning by-law Amendment application to permit a mixed-use building with 33- and 19-storey tower elements, containing 401 dwelling units and 75 square metres of non-residential gross floor area. The proposal includes heritage conservation…
    File 21 233780 STE 11 OZ · submitted Nov 3, 2021 · City record
  5. 5
    906 Yonge St · 200 m away
    Site Plan: City review of the design and layout of a new building

    City planners approved the site plan, with conditions to meet before a building permit.

    Site Plan Approval for a 40-storey and 23-storey building, containing a combined total of 410 dwelling units and 760 square metres of non-residential gross floor area.
    File 21 233790 STE 11 SA · submitted Nov 3, 2021 · City record
  6. 6
    25 Mc Murrich St · 234 m away
    Official Plan / Rezoning: a request to change the Official Plan or zoning so something new can be built

    The Ontario Land Tribunal (formerly the OMB) approved it.

    Zoning by-law Amendment application to permit a mixed-use building with 33- and 19-storey tower elements, containing 401 dwelling units and 75 square metres of non-residential gross floor area. The proposal includes heritage conservation…
    File 21 233780 STE 11 OZ · submitted Nov 3, 2021 · City record
  7. 7
    25 Mc Murrich St · 234 m away
    Site Plan: City review of the design and layout of a new building

    City planners approved the site plan, with conditions to meet before a building permit.

    Site Plan Approval for a 40-storey and 23-storey building, containing a combined total of 410 dwelling units and 760 square metres of non-residential gross floor area.
    File 21 233790 STE 11 SA · submitted Nov 3, 2021 · City record
Short-term rentals nearby48 registered homesWithin 250 mShort Term Rentals Registration

48 homes within 250 m are registered with the City as short-term rentals (stays of less than 28 days, like Airbnb). That's more than at almost all Toronto addresses.

Development Applications; Committee of Adjustment Applications; Short Term Rentals Registration.

02City services

ItemFindingPrecisionSource
Garbage and recyclingWednesdaysThis addressSolid Waste Collection Schedule

Next: November 11: recycling and green bin. November 18: garbage, green bin and yard waste. Green bin goes out every week; garbage and recycling alternate.

City councillorDianne SaxeWard 11Councillor_Saxe@toronto.ca · 416-392-4009

05Quick answers about 835 Yonge St

Is 835 Yonge St in a flood plain?

No. TRCA maps it outside river flood and lake shoreline hazard areas. Basement flooding from sewers can still happen anywhere. Source: TRCA Regulation mapping 2025.

What is being built near 835 Yonge St?

There are 7 active planning applications within 250 metres (five approved, two approved by the tribunal). The closest is at 874 Yonge St, 81 m away. Source: Development Applications; Committee of Adjustment Applications.

Has 835 Yonge St been renovated?

Yes. The City has 1 building permit on record, 1 in the last 5 years. Source: Building Permits.

Is 835 Yonge St a heritage property?

Yes. It is individually designated under the Ontario Heritage Act (Part IV). Changes to its heritage features need a heritage permit from the City. Source: Heritage Register.

When is garbage day at 835 Yonge St?

Collection is on Wednesdays. Green bin goes out every week; garbage and recycling alternate weeks. The next garbage pickup is Nov 18, 2026. Source: Solid Waste Collection Schedule.

Answers are generated from the data on this page and update when the data changes.

06From the archives

82 Davenport Road — Church Street Extension
1930 · 38 m away82 Davenport Road — Church Street ExtensionCity of Toronto Archives, Fonds 200, Series 372, Subseries 3, Item 945
33 Davenport Road — Church Street Extension
1930 · 38 m away33 Davenport Road — Church Street ExtensionCity of Toronto Archives, Fonds 200, Series 372, Subseries 3, Item 944
View of store window display on west side of Yonge Street, north of Davenport
1975 · 38 m awayView of store window display on west side of Yonge Street, north of DavenportCity of Toronto Archives, Fonds 1526, File 1, Item 118
35-37 Davenport Road — Church Street Extension
1930 · 38 m away35-37 Davenport Road — Church Street ExtensionCity of Toronto Archives, Fonds 200, Series 372, Subseries 3, Item 926
View of drapery store on west side of Yonge Street, north of Davenport
1975 · 38 m awayView of drapery store on west side of Yonge Street, north of DavenportCity of Toronto Archives, Fonds 1526, File 1, Item 126
View of Ridpath's on west side of Yonge Street, north of Davenport Road
1973 · 38 m awayView of Ridpath's on west side of Yonge Street, north of Davenport RoadCity of Toronto Archives, Fonds 1526, File 1, Item 116
Yonge Street south from Davenport Road
1939 · 38 m awayYonge Street south from Davenport RoadCity of Toronto Archives, Fonds 1231, Item 1681
Severn, John, brewery, Yonge St., n.e. corner Church St.
1870 · 38 m awaySevern, John, brewery, Yonge St., n.e. corner Church St. Courtesy of Toronto Public Library
21-23 Davenport Road — Church Street Extension
1930 · 38 m away21-23 Davenport Road — Church Street ExtensionCity of Toronto Archives, Fonds 200, Series 372, Subseries 3, Item 923