89 Cavell Ave

89 Cavell Ave is in Mimico-Queensway. It's outside TRCA flood hazard areas and there are 21 planning applications nearby (15 under review, three approved, two under appeal after approval, one other).

Data as of Nov 8, 2026 · Every item lists its source

Follow this address
Key findings
  • 5 building permits in the last 5 years.
  • Outside TRCA flood hazard areas.
  • 21 planning applications within 250 m: 15 under review, three approved, two under appeal after approval, one other.
Building permits5in the last 5 years
Applications nearby21active, within 250 m
Flood hazardOutsideTRCA mapping
Next collectionNov 10garbage, green bin and yard waste
Royal York RdCavell AveSuperior AveNewcastle StManchester StSkelton StStation RdBlue Goose StBurlington StAlexander StStanley AveVictoria StAlbert Ave123456789101112Map data: City of Toronto (Toronto Centreline)Cavell AveSuperior AveNewcastle StBurlington StStation RdBlue Goose StStanley Ave123456789101112Map data: City of Toronto (Toronto Centreline)
The red dot is 89 Cavell Ave. The circle shows 250 metres, about a 3-minute walk. Numbers match the applications in “What’s changing nearby”.

04The building

ItemFindingPrecisionSource
Building orders and noticesNone on recordThis addressBuilding Construction/Demolition Violations
Building permits, last 5 years5 permitsThis addressBuilding Permits · 14 on record

5 building permits in the last 5 years, for 1 project. Together they added 4 new homes. For comparison, about 1 in 10 Toronto addresses had any permit in that time. Permits show work the City approved; they don't show work done without a permit.

Short-term rentalNot registeredThis addressShort Term Rentals Registration
Heritage statusNot on the Heritage RegisterThis addressHeritage Register

It isn't listed or designated on the City's Heritage Register.

Permit history: 4 projects from 14 permits
  • Underpinning, deck or porch and more · revision issued · issued Sep 29, 2022
    BASEMENT LAYOUT.Proposal to rebuild front porch, interior alterations and underpinning · 5 permits in this project (such as building, plumbing and heating) · Permit 22 193946
  • New Building · completed Feb 22, 2021
    Rev #1-Revise layout, windows, balcony, hvacproposed to construct new triplex. · 7 permits in this project (such as building, plumbing and heating) · Permit 19 109759
  • Demolition · completed Jan 28, 2021
    Proposed to construct new triplex. · Permit 19 111377
  • New Building · completed Oct 2, 2018
    Proposal to construct ground floor, 2nd floor, and 3rd floor addition, more than 50% of the existing main walls above the ground are being removed, interior alteration to existing ground floor, and… · Permit 18 203474

05Risks and environment

ItemFindingPrecisionSource
River flood hazardOutsideThis addressTRCA Regulation mapping 2025
Lake shoreline hazardOutsideThis addressTRCA Regulation mapping 2025
TRCA regulated areaOutsideThis addressTRCA Regulation mapping 2025

TRCA's maps show this address is outside the areas that could flood from rivers in a major storm (TRCA plans for a storm like Hurricane Hazel in 1954) and outside lake shoreline hazards. Basement flooding from overloaded sewers can still happen anywhere in the city.

Lead in tap-water tests, postal area M8V0.5% of tests above Ontario's limitYour area · M8VNon Regulated Lead Sample · 202 tests, Mar 24, 2014 to Sep 7, 2026

In postal area M8V, 1 of 202 home tap-water samples (0.5%) tested above Ontario's limit for lead (10 micrograms per litre). Across Toronto, 2.0% of samples did, so M8V is lower than the city overall. Health Canada recommends a stricter limit of 5 micrograms per litre: 3 samples here (1.5%) were above it. These are voluntary tests, mostly from older homes, so they don't tell you about this house. Lead comes from old pipes and plumbing, not the City's treatment plants. If your home was built before the mid-1950s, you can get a free test kit by calling 311.

Air quality now2 · Low riskYour areaEnvironment and Climate Change Canada · hourly

Air Quality Health Index from Environment and Climate Change Canada's Toronto Downtown station, 10.1 km away, measured 11:00 AM EST Sunday 8 November 2026. Forecast high for the next 24 hours: 2 (low risk). The scale runs from 1 to 10+; 1 to 3 is low risk.

TRCA mapping is for screening, not site-specific decisions. Lead results are voluntary samples from homes in the postal area, not this address.

01What’s changing nearby

21 active planning applications within 250 m (about a 3-minute walk): 15 under review, three approved, two under appeal after approval, one other. That's more than at almost all Toronto addresses.

  1. 1
    2 Audley St · 55 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed 40-storey, 123 metre, mixed-use building containing 413 residential units.
    File 24 174546 WET 03 SA · submitted Jul 4, 2024 · City record
  2. 2
    2 Audley St · 55 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed mixed-use building containing 1,058 units, 23-storey and 27-storey towers atop a nine-storey base building.
    File 24 175201 WET 03 SA · submitted Jul 5, 2024 · City record
  3. 3
    2 Audley St · 55 m away
    Official Plan / Rezoning: a request to change the Official Plan or zoning so something new can be built

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposal includes 5 mixed-use towers, ranging in heights of 34-54 storeys with 2,631 residential rental units and 415 vehicular parking spaces within a two-level below-grade parking structure. The proposal also conveys 5,499 square metres…
    File 26 191872 WET 03 OZ · submitted Jun 26, 2026 · City record
  4. 4
    29 Portland St · 90 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed mixed-use building containing 1,058 units, 23-storey and 27-storey towers atop a nine-storey base building.
    File 24 175201 WET 03 SA · submitted Jul 5, 2024 · City record
  5. 5
    29 Portland St · 90 m away
    Subdivision: a request to divide land into new lots and streets

    City planners are reviewing it. Residents can comment before a decision is made.

    Draft Plan of Subdivision in order to establish two mixed use development blocks (Blocks 1 and 2), two park blocks (Block 3 and 4) and a road widening (Block 5) for the extension of Newcastle Street.
    File 21 172862 WET 03 SB · submitted Jun 18, 2021 · City record
  6. 6
    29 Portland St · 90 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed 40-storey, 123 metre, mixed-use building containing 413 residential units.
    File 24 174546 WET 03 SA · submitted Jul 4, 2024 · City record
  7. 7
    10 Audley St · 93 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed 40-storey, 123 metre, mixed-use building containing 413 residential units.
    File 24 174546 WET 03 SA · submitted Jul 4, 2024 · City record
  8. 8
    10 Audley St · 93 m away
    Subdivision: a request to divide land into new lots and streets

    City planners are reviewing it. Residents can comment before a decision is made.

    Draft Plan of Subdivision in order to establish two mixed use development blocks (Blocks 1 and 2), two park blocks (Block 3 and 4) and a road widening (Block 5) for the extension of Newcastle Street.
    File 21 172862 WET 03 SB · submitted Jun 18, 2021 · City record
  9. 9
    10 Audley St · 93 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed mixed-use building containing 1,058 units, 23-storey and 27-storey towers atop a nine-storey base building.
    File 24 175201 WET 03 SA · submitted Jul 5, 2024 · City record
  10. 10
    59 Portland St · 110 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed mixed-use building containing 1,058 units, 23-storey and 27-storey towers atop a nine-storey base building.
    File 24 175201 WET 03 SA · submitted Jul 5, 2024 · City record
  11. 11
    59 Portland St · 110 m away
    Site Plan: City review of the design and layout of a new building

    City planners are reviewing it. Residents can comment before a decision is made.

    Proposed 40-storey, 123 metre, mixed-use building containing 413 residential units.
    File 24 174546 WET 03 SA · submitted Jul 4, 2024 · City record
  12. 12
    59 Portland St · 110 m away
    Subdivision: a request to divide land into new lots and streets

    City planners are reviewing it. Residents can comment before a decision is made.

    Draft Plan of Subdivision in order to establish two mixed use development blocks (Blocks 1 and 2), two park blocks (Block 3 and 4) and a road widening (Block 5) for the extension of Newcastle Street.
    File 21 172862 WET 03 SB · submitted Jun 18, 2021 · City record
Short-term rentals nearby1 registered homeWithin 250 mShort Term Rentals Registration

1 home within 250 m is registered with the City as short-term rentals (stays of less than 28 days, like Airbnb). That's about typical for Toronto (the typical address has 2).

Licensed rooming houses nearby0 licensed housesWithin 250 mMulti-Tenant (Rooming) House Licences

No licensed rooming houses within 250 m.

New storefront businesses0 in 90 daysWithin 250 mBusiness Licences and Permits

No new storefront business licences within 250 m in the last 90 days.

Development Applications; Committee of Adjustment Applications; Short Term Rentals Registration.

06Safety

Police recorded 73 major crimes within 500 m from Oct 2025 to Sep 2026: 39 assaults, 16 car thefts, 12 break-ins, 5 thefts over $5,000 and 1 robbery. Per resident, in Mimico-Queensway in 2025, assaults were above the Toronto rate; break-ins and robberies were below it. Police place each incident at the nearest intersection, so these figures describe the area, not this address.

Major crimeWithin 500 m, 12 monthsMimico-Queensway, per 100,000 (2025)Toronto
Assaults394209 above Toronto768
Break-ins12133 below Toronto190
Car thefts16224 close to Toronto225
Robberies142 below Toronto79
Thefts over $5,000566 close to Toronto61

Toronto Police Service Public Safety Data Portal: Major Crime Indicators (Oct 1, 2025 to Sep 30, 2026) and Neighbourhood Crime Rates. Includes reported incidents only.

03Getting around

The nearest subway station is Old Mill Station (Line 2), 3.6 km away. Within a 5-minute walk there are 3 TTC stops served by routes 76 and 80, with about 112 departures on a typical weekday. The nearest GO train station is Mimico GO, 0.4 km away, with 74 train stops on a weekday.

ItemFindingPrecisionSource
Nearest subway stationOld Mill Station3.6 kmTTC · Line 2 · too far to walk
Nearest GO train stationMimico GO362 mGO Transit · 74 train stops on a weekday
Bus stopNewcastle St at Windsor St - Mimico GO Station302 mTTC routes 80
Bus stopPortland St at Milton St West Side342 mTTC routes 76
Bus stopPortland St at Wesley St West Side388 mTTC routes 76

TTC and GO Transit schedules for a typical weekday (Nov 11, 2026). Walking times are estimates.

07Schools and community

These are the closest public and Catholic schools by distance. They may not be the schools assigned to this address: school boards set their own attendance areas, so check with the Toronto District School Board or Toronto Catholic District School Board.

  • St Leo Catholic School · elementary · 397 m
    TCDSB · Catholic · grades JK-8 · 405 students. Grade 6 provincial tests: 96% met the standard in reading and 73% in math (Toronto schools: 87% and 54%).
  • David Hornell Junior School · elementary · 429 m
    TDSB · Public · grades JK-5 · 230 students
  • George R Gauld Junior School · elementary · 551 m
    TDSB · Public · grades JK-5 · 250 students
  • Bishop Allen Academy Catholic Secondary School · secondary · 2.1 km
    TCDSB · Catholic · grades 9-12 · 1,460 students. 94% passed the Grade 10 literacy test on the first try (Toronto schools: 84%).
  • Lakeshore Collegiate Institute · secondary · 2.7 km
    TDSB · Public · grades 9-12 · 650 students. 75% passed the Grade 10 literacy test on the first try (Toronto schools: 84%).

Private schools within 1 km: Phoenix Montessori School, Oak Learners.

Ontario Ministry of Education, School Information and Student Demographics (2026); test results are EQAO results reported by the Ministry.

Within 500 m (about a 6-minute walk): four licensed child care centres, one EarlyON centre, no privately owned public spaces and one shelter or respite site.

Licensed child carePlasp - David Hornell Junior School430 m32 Victoria St · 58 spaces · kindergarten, school age · in the $10-a-day program (CWELCC) · fee subsidies
Licensed child careRec Room Child Care @mimico441 m46 Mimico Ave · 36 spaces · toddler, preschool · in the $10-a-day program (CWELCC)
Licensed child carePhoenix Montessori School Inc.480 m2 Station Rd · 125 spaces · infant, toddler, preschool, kindergarten
Licensed child careMartin Luther Child Care - Lakeshore489 m2379 Lake Shore Blvd W · 42 spaces · preschool, school age · in the $10-a-day program (CWELCC) · fee subsidies
EarlyON centreMimico Library EarlyON Child and Family Centre280 m47 Station Rd · free programs for children up to 6 and their caregivers
Shelter or respite siteSVDP Elisa House327 m60 Newcastle St · Women · 29 beds

City of Toronto: Licensed Child Care Centres, EarlyON Child and Family Centres, POPS, and Daily Shelter Occupancy (Nov 6, 2026). Confidential shelter locations are not published.

08Your neighbourhood

Mimico-Queensway had 17,045 residents in 2021. The median household income was $84,000, about the same as the typical Toronto neighbourhood ($85,000). 47% of households rent (typical neighbourhood: 46%). 40% of renters spend 30% or more of their income on housing. 22% of workers commuted by transit and 5% walked or cycled (typical neighbourhood: 26% and 5%). The most common first languages other than English and French are Polish (4.3%), Tibetan (3.4%) and Portuguese (2.4%). Source: 2021 Census; the next census was taken in 2026.

Residents (2021)17,045Mimico-Queensway
Median household income$84,000typical neighbourhood $85,000
Households that rent47%typical neighbourhood 46%
Commute by transit22%typical neighbourhood 26%

In October 2025, the average rent for a two-bedroom in a purpose-built rental building in Etobicoke was $2,031, up 4% from a year earlier. Across Toronto: $2,055. 2.1% of these apartments were vacant. These are averages paid by all tenants, including long-term ones, across a large area; new listings usually cost more.

Average rent, October 2025EtobicokeChange in a yearCity of Toronto
Studio$1,533+4%$1,499
1 bedroom$1,700+2%$1,763
2 bedrooms$2,031+4%$2,055
3 bedrooms or more$2,438+14%$2,361

Source: CMHC, Rental Market Survey (October 2025), purpose-built rental apartments. Adapted by My Address in Toronto.

02City services

ItemFindingPrecisionSource
Garbage and recyclingTuesdaysThis addressSolid Waste Collection Schedule

Next: November 10: garbage, green bin and yard waste. November 17: recycling and green bin. Green bin goes out every week; garbage and recycling alternate.

City councillorAmber MorleyWard 3Councillor_Morley@toronto.ca · 416-397-9273

09Quick answers about 89 Cavell Ave

Is 89 Cavell Ave in a flood plain?

No. TRCA maps it outside river flood and lake shoreline hazard areas. Basement flooding from sewers can still happen anywhere. Source: TRCA Regulation mapping 2025.

What is being built near 89 Cavell Ave?

There are 21 active planning applications within 250 metres (15 under review, three approved, two under appeal after approval, one other). The closest is at 2 Audley St, 55 m away. Source: Development Applications; Committee of Adjustment Applications.

Has 89 Cavell Ave been renovated?

Yes. The City has 14 building permits on record, 5 in the last 5 years. Source: Building Permits.

Is 89 Cavell Ave a heritage property?

No. It isn't listed or designated on the City's Heritage Register. Source: Heritage Register.

How far is 89 Cavell Ave from the subway?

The nearest station is Old Mill Station (Line 2), 3.6 km away. 3 TTC stops are within a 5-minute walk. Source: TTC and GO Transit schedules.

What schools are near 89 Cavell Ave?

The closest are St Leo Catholic School, David Hornell Junior School and Bishop Allen Academy Catholic Secondary School. These may not be the assigned schools; check with the school board. Source: Ontario Ministry of Education school information.

How much crime is there near 89 Cavell Ave?

Police recorded 73 major crimes within 500 m from Oct 2025 to Sep 2026: 39 assaults, 16 car thefts, 12 break-ins, 5 thefts over $5,000 and 1 robbery. Per resident, in Mimico-Queensway in 2025, assaults were above the Toronto rate; break-ins and robberies were below it. Police place each incident at the nearest intersection, so these figures describe the area, not this address. Source: Toronto Police Service.

When is garbage day at 89 Cavell Ave?

Collection is on Tuesdays. Green bin goes out every week; garbage and recycling alternate weeks. The next garbage pickup is Nov 10, 2026. Source: Solid Waste Collection Schedule.

Answers are generated from the data on this page and update when the data changes.

10From the archives

No archive photos have been located within 250 metres yet.

Photo locations are matched from each photo’s title against City street and address data, so some may be off. Report a wrong location

89 Cavell Ave, Toronto M8V: permits, flood risk and what's planned nearby · My Address in Toronto