Planning application · Rezoning

59-storey building

100 Lombard St and 1 more address · Downtown Yonge East · Ward 13 Toronto Centre

A request to change the zoning to allow a 59-storey building, with 480 homes. It was submitted in August 2022 and has been appealed to the Ontario Land Tribunal, which will make the final decision.

City file 22 192723 STE 13 OZ · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedAug 18, 2022
  2. Community meetingMar 2, 2023
  3. NowAppealed to the Ontario Land Tribunal
  4. NextTribunal hearing and decision

01Have your say

Nothing scheduled right now

Because the application has been appealed, the Ontario Land Tribunal, not City Council, will make the decision. No public meeting or comment deadline is set at the moment.

Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Chris Moise, can tell you how the City is handling the appeal.

02What’s proposed

One 59-storey building with 480 homes.

20 storeys40 storeys60 storeys59PROPOSED
Heights in storeys, from the application.
Homes
480
Height
59 storeys
Total floor space
38,672 m²
What it needs
A change to the zoning (rules for what can be built where)
The applicant’s description
Zoning By-law Amendment application to permit a 59-storey mixed-use building containing 480 dwelling units, 4,321 square metres of office space, and 616 square metres of retail space.. A Site Plan Application (22 192721 STE 13 SA) has been submitted concurrently with the application.
From the City’s development applications data, as written.

03Timeline

  1. Aug 18, 2022Application submitted to the City.
  2. Aug 18, 2022A related site plan application is filed: 59-storey building.
  3. Mar 2, 2023Community consultation meeting.
  4. —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.

04City files and documents

TypeFileStatus
RezoningFile 22 192723 STE 13 OZUnder appealDocuments and reports on the City’s site
Site planFile 22 192721 STE 13 SAIn progressSee its page

Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

Jarvis StAdelaide StChurch StRichmond StYonge StKing StFront StWellington StLower Jarvis StToronto StCourt StLombard StVictoria StGeorge StFrederick StColborne StScott StThe EsplanadeJenoves Pl123456Map data: City of Toronto (Toronto Centreline)Jarvis StAdelaide StChurch StKing StRichmond StFront StToronto StCourt StLombard StBerti StGeorge StColborne StScott StMarket St123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    59-storey building (480 homes)
    86 Lombard St · next door

    City planners are reviewing it

  2. 2
    65-storey building (600 homes)
    110 Adelaide St E · about 70 m

    Appealed to the Ontario Land Tribunal

  3. 3
    65-storey building (600 homes)
    110 Adelaide St E · about 70 m

    Appealed to the Ontario Land Tribunal

  4. 4
    Subdivision
    114 Church St · about 160 m

    City planners are reviewing it

  5. 5
    Site plan
    134 Jarvis St · about 210 m

    City planners are reviewing it

  6. 6
    63-storey building (369 homes)
    65 Adelaide St E · about 210 m

    City planners are reviewing it

All applications in progress in Ward 13

06Quick answers about this application

What is proposed at 100 Lombard St?

One 59-storey building with 480 homes, 59 storeys, under City file 22 192723 STE 13 OZ. Source: Development Applications, as of Nov 13, 2026.

Has the 100 Lombard St development been approved?

Not yet. It has been appealed to the Ontario Land Tribunal, which will make the final decision. Source: Development Applications, as of Nov 13, 2026.

Can I comment on it?

No meeting or comment deadline is scheduled right now. Follow the application to get an email if one is set. Source: Development Applications and Public Notices, as of Nov 13, 2026.

Who is the councillor for 100 Lombard St?

Chris Moise, Ward 13 Toronto Centre. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.