Planning application · Official Plan and rezoning

56-storey building

110 Maitland St and 2 more addresses · Church-Wellesley · Ward 13 Toronto Centre

A request to change the Official Plan and zoning to allow a 56-storey building, with 579 homes. It was submitted in July 2025 and has been appealed to the Ontario Land Tribunal, which will make the final decision.

City file 25 187527 STE 13 OZ · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedJul 3, 2025
  2. Notice to neighboursAug 22, 2025
  3. Community meetingDec 10, 2025
  4. NowAppealed to the Ontario Land Tribunal
  5. NextTribunal hearing and decision

01Have your say

Nothing scheduled right now

Because the application has been appealed, the Ontario Land Tribunal, not City Council, will make the decision. No public meeting or comment deadline is set at the moment.

Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Chris Moise, can tell you how the City is handling the appeal.

02What’s proposed

One 56-storey building with 579 homes.

20 storeys40 storeys60 storeys56PROPOSED
Heights in storeys, from the application.
Homes
579
Height
56 storeys
Total floor space
39,450 m²
What it needs
Changes to the Official Plan and zoning (rules for what can be built where)
The applicant’s description
Combined Official Plan & Zoning By-law Amendment for a 56-storey mixed-use building. The proposed building contains a total of 579 dwelling units, of which 36 are rental replacement units, and a total of approximately 4,739 square metres of institutional space for the Garry Hurvitz Centre for Community Mental Health at SickKids located in 440 Jarvis Street.
From the City’s development applications data, as written.

03Timeline

  1. Jul 3, 2025Application submitted to the City.
  2. Aug 22, 2025City notice: Notice of Application - 110 and 114 Maitland Street and 440 Jarvis Street. Read the notice
  3. Sep 22, 2025A related site plan application is filed: 56-storey building.
  4. Dec 10, 2025Community consultation meeting.
  5. —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.

04City files and documents

TypeFileStatus
Official Plan and rezoningFile 25 187527 STE 13 OZUnder appealDocuments and reports on the City’s site
Site planFile 25 228933 STE 13 SAIn progressSee its page

Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

Yonge StWellesley StChurch StJarvis StCarlton StMaitland StAlexander StWood StGrenville StMutual StHomewood AveMaribeth AveGranby St123456Map data: City of Toronto (Toronto Centreline)Church StWellesley StJarvis StCarlton StMaitland StAlexander StMutual StWood StGranby St123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    56-storey building (579 homes)
    440 Jarvis St · about 50 m

    City planners are reviewing it

  2. 2
    28-storey building (258 homes)
    68 Wellesley St E · about 150 m

    Appealed to the Ontario Land Tribunal

  3. 3
    48-storey building with shops (574 homes)
    508 Church St · about 170 m

    Appealed to the Ontario Land Tribunal

  4. 4
    14-storey building (160 homes)
    506 Church St · about 180 m

    Appealed to the Ontario Land Tribunal

  5. 5
    197 homes
    506 Church St · about 180 m

    City planners are reviewing it

  6. 6
    48-storey building with shops (574 homes)
    506 Church St · about 180 m

    Appealed to the Ontario Land Tribunal

All applications in progress in Ward 13

06Quick answers about this application

What is proposed at 110 Maitland St?

One 56-storey building with 579 homes, 56 storeys, under City file 25 187527 STE 13 OZ. Source: Development Applications, as of Nov 13, 2026.

Has the 110 Maitland St development been approved?

Not yet. It has been appealed to the Ontario Land Tribunal, which will make the final decision. Source: Development Applications, as of Nov 13, 2026.

Can I comment on it?

No meeting or comment deadline is scheduled right now. Follow the application to get an email if one is set. Source: Development Applications and Public Notices, as of Nov 13, 2026.

Who is the councillor for 110 Maitland St?

Chris Moise, Ward 13 Toronto Centre. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

110 Maitland St development: 56-storey building (under appeal) · My Address in Toronto