Three towers, up to 45 storeys with shops
1799 St Clair Ave W · Weston-Pelham Park · Ward 9 Davenport
A request to change the Official Plan and zoning to allow a 45-storey building, with 1,174 homes. It was submitted in August 2021 and has been appealed to the Ontario Land Tribunal, which will make the final decision.
City file 21 196875 STE 09 OZ · Data as of Nov 13, 2026 · Every item lists its source
- SubmittedAug 11, 2021
- Community meetingMar 29, 2022
- NowAppealed to the Ontario Land Tribunal
- NextTribunal hearing and decision
01Have your say
Because the application has been appealed, the Ontario Land Tribunal, not City Council, will make the decision. No public meeting or comment deadline is set at the moment.
Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Alejandra Bravo, can tell you how the City is handling the appeal.
02What’s proposed
One 45-storey building with 1,174 homes and space for shops or offices.
- Homes
- 1,174
- Height
- 45 storeys
- Shops or offices
- 11,025 m² of floor space
- Total floor space
- 103,733 m²
- What it needs
- Changes to the Official Plan and zoning (rules for what can be built where)
The applicant’s description
Official Plan and Zoning By-law Amendment application to facilitate the development of the site for 3 mixed-use towers having heights of 30, 40, and 45 storeys atop podiums with ranging heights of 3-8 storeys. The proposed non-residential gross floor area is 11,025 square metres, and the proposed residential gross floor area is 97,037 square metres. A total of 1151 residential dwelling units are proposedFrom the City’s development applications data, as written.
03Timeline
- Aug 11, 2021Application submitted to the City.
- Aug 11, 2021A related subdivision application is filed: Subdivision.
- Mar 29, 2022Community consultation meeting.
- Apr 29, 2022A related site plan application is filed: Site plan.
- —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.
04City files and documents
| Type | File | Status | |
|---|---|---|---|
| Official Plan and rezoning | File 21 196875 STE 09 OZ | Under appeal | Documents and reports on the City’s site |
| Subdivision | File 21 196867 STE 09 SB | In progress | See its page |
| Site plan | File 22 140038 STE 09 SA | In progress | See its page |
Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.
05Nearby applications
The red dot is this application. The circle shows 400 metres, about a 5-minute walk.
- 1
- 2
- 3
- 4
- 5
- 6
06Quick answers about this application
What is proposed at 1799 St Clair Ave W?
One 45-storey building with 1,174 homes and space for shops or offices, 45 storeys, under City file 21 196875 STE 09 OZ. Source: Development Applications, as of Nov 13, 2026.
Has the 1799 St Clair Ave W development been approved?
Not yet. It has been appealed to the Ontario Land Tribunal, which will make the final decision. Source: Development Applications, as of Nov 13, 2026.
Can I comment on it?
No meeting or comment deadline is scheduled right now. Follow the application to get an email if one is set. Source: Development Applications and Public Notices, as of Nov 13, 2026.
Who is the councillor for 1799 St Clair Ave W?
Alejandra Bravo, Ward 9 Davenport. Source: City Wards and Councillors, as of Nov 13, 2026.
Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.