A request to approve the detailed design of a 49-storey building, with 580 homes. It was submitted in September 2022 and has been appealed to the Ontario Land Tribunal, which will make the final decision.

City file 22 206826 WET 03 SA · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedSep 21, 2022
  2. NowAppealed to the Ontario Land Tribunal
  3. NextTribunal hearing and decision

01Have your say

Nothing scheduled right now

Because the application has been appealed, the Ontario Land Tribunal, not City Council, will make the decision. No public meeting or comment deadline is set at the moment.

Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Amber Morley, can tell you how the City is handling the appeal.

02What’s proposed

One 49-storey building with 580 homes, on the site of the 31-storey rental building at 25 Mabelle Ave.

10 storeys20 storeys30 storeys40 storeys50 storeys4931PROPOSEDON THE SITE TODAY
Heights in storeys, from the application. The existing building is from City records.
Homes
580
Height
49 storeys
What it needs
Site plan approval (the City’s review of the detailed design)
The applicant’s description
Proposal to redevelop the site with a 49 storey mixed use building containing 79 square metres of retail gross floor area, 580 residential condominium units and 5 levels of below grade parking. The new building is proposed to be constructed to the west of the existing residential building at 25 Mabelle Avenue.
From the City’s development applications data, as written.

03Timeline

  1. Sep 21, 2022Application submitted to the City.
  2. —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.

04City files and documents

TypeFileStatus
Site planFile 22 206826 WET 03 SAUnder appealDocuments and reports on the City’s site

Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.

Earlier at this address

05Nearby applications

Bloor StIslington AveMichael Power PlResurrection RdFieldway RdGreen LanesMonkton AveClissold RdMeadowvale DrMabelle AveKenway Rd123456Map data: City of Toronto (Toronto Centreline)Bloor StGreen LanesFieldway RdMeadowvale DrMabelle AveKenway Rd123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    Subdivision
    3326 Bloor St W · about 140 m

    City planners are reviewing it

  2. 2
    Split the lot
    36 Clissold Rd · about 200 m

    Appealed to the Toronto Local Appeal Body

  3. 3
    61-storey building
    1243 Islington Ave · about 240 m

    City planners are reviewing it

  4. 4
    35-storey building (375 homes)
    1276 Islington Ave · about 250 m

    City planners are reviewing it

  5. 5
    27-storey building (325 homes)
    16 Cordova Ave · about 330 m

    City planners are reviewing it

  6. 6
    Consent
    56 Fieldway Rd · about 400 m

    Waiting for a hearing date

All applications in progress in Ward 3

06Quick answers about this application

What is proposed at 25 Mabelle Ave?

One 49-storey building with 580 homes, 49 storeys, under City file 22 206826 WET 03 SA. Source: Development Applications, as of Nov 13, 2026.

Has the 25 Mabelle Ave development been approved?

Not yet. It has been appealed to the Ontario Land Tribunal, which will make the final decision. Source: Development Applications, as of Nov 13, 2026.

Can I comment on it?

No meeting or comment deadline is scheduled right now. Follow the application to get an email if one is set. Source: Development Applications and Public Notices, as of Nov 13, 2026.

Who is the councillor for 25 Mabelle Ave?

Amber Morley, Ward 3 Etobicoke-Lakeshore. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

25 Mabelle Ave development: 49-storey building (under appeal) · My Address in Toronto