Addition
3180-3182 Yonge St · Lawrence Park North · Ward 8 Eglinton-Lawrence
The owner is asking for exceptions to the zoning rules to facilitate in the development of the already approved 11-storey building by seeking to permit four (4) additional storeys, plus a mechanical amenity level, for a total height of 15-storeys, includi. The decision has been appealed.
City file A0312/24NY · Data as of Nov 13, 2026 · Every item lists its source
- SubmittedJun 13, 2024
- HearingAug 29, 2024
- DecisionRefused by the Committee
- NowAppealed to the Ontario Land Tribunal
- NextAppeal hearing and decision
01Have your say
Because the application has been appealed, the Ontario Land Tribunal, not the Committee of Adjustment, will make the decision. No public meeting or comment deadline is set at the moment.
Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Mike Colle, can tell you how the City is handling the appeal.
02What’s proposed
To facilitate in the development of the already approved 11-storey building by seeking to permit four (4) additional storeys, plus a mechanical amenity level, for a total height of 15-storeys, including 49 additional dwelling units, increasing the total number dwelling units to 153 units. Related Planning Applications: 20 214204 NNY 08 OZ & 21 162972 NNY 08 SA.
The application’s description, from the City’s Committee of Adjustment data. A minor variance is permission for a small exception to the zoning rules, such as height or lot coverage.
03Timeline
- Jun 13, 2024Application submitted to the City.
- Aug 29, 2024Committee of Adjustment hearing: refused.
- —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.
04City files and documents
| Type | File | Status | |
|---|---|---|---|
| Minor variance | File A0312/24NY | Under appeal | The City’s Application Information Centre |
| Condominium | File 21 231950 NNY 08 CD | In progress | See its page |
Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.
Earlier at this address
- Rezoning · 2020 · closed · City record
05Nearby applications
The red dot is this application. The circle shows 400 metres, about a 5-minute walk.
- 1
- 2
- 3
- 4
- 5
- 6
06Quick answers about this application
What is being built at 3180-3182 Yonge St?
To facilitate in the development of the already approved 11-storey building by seeking to permit four (4) additional storeys, plus a mechanical amenity level, for a total height of 15-storeys, including 49 additional dwelling units, increasing the total… (file A0312/24NY). Source: Committee of Adjustment Applications, as of Nov 13, 2026.
Was the application at 3180-3182 Yonge St approved?
Appealed to the Ontario Land Tribunal. Source: Committee of Adjustment Applications, as of Nov 13, 2026.
Who is the councillor for 3180-3182 Yonge St?
Mike Colle, Ward 8 Eglinton-Lawrence. Source: City Wards and Councillors, as of Nov 13, 2026.
Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.