New semi-detached house
5 Marina Ave · Long Branch · Ward 3 Etobicoke-Lakeshore
The owner is asking for exceptions to the zoning rules to construct a new semi-detached dwelling with an attached garage. The decision has been appealed.
City file A0027/21EYK · Data as of Nov 13, 2026 · Every item lists its source
- SubmittedJan 15, 2021
- HearingFeb 10, 2022
- DecisionRefused by the Committee
- NowAppealed to the Toronto Local Appeal Body
- NextAppeal hearing and decision
01Have your say
Because the application has been appealed, the Toronto Local Appeal Body, not the Committee of Adjustment, will make the decision. No public meeting or comment deadline is set at the moment.
Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Amber Morley, can tell you how the City is handling the appeal.
02What’s proposed
To construct a new semi-detached dwelling with an attached garage.
The application’s description, from the City’s Committee of Adjustment data. A minor variance is permission for a small exception to the zoning rules, such as height or lot coverage.
03Timeline
- Jan 15, 2021Application submitted to the City.
- Jan 15, 2021A related consent application is filed: Split the lot.
- Feb 10, 2022Committee of Adjustment hearing: refused.
- Nov 1, 2023Building permit issued: Proposal to demolish existing dwelling and sever lot into two parcels to construct new 2 unit semi-detached dwellings with rear deck and integral garage
- —Appealed to the Toronto Local Appeal Body. Date not published in the City’s data; from now on we record the date we first see each change.
04City files and documents
| Type | File | Status | |
|---|---|---|---|
| Minor variance | File A0027/21EYK | Under appeal | The City’s Application Information Centre |
| Consent | File B0006/21EYK | Under appeal | See its page |
Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.
05Elsewhere on this site
New-building and demolition permits at 5 Marina Ave since this application was filed.
- •New building: 2 homesPermit 23 142069 BLD
Under construction: permit issued Nov 1, 2023
Proposal to demolish existing dwelling and sever lot into two parcels to construct new 2 unit semi-detached dwellings with rear deck and integral garage
06Nearby applications
The red dot is this application. The circle shows 400 metres, about a 5-minute walk.
- 1
- 2
- 3
- 4
- 5
- 6
07Quick answers about this application
What is being built at 5 Marina Ave?
To construct a new semi-detached dwelling with an attached (file A0027/21EYK). Source: Committee of Adjustment Applications, as of Nov 13, 2026.
Was the application at 5 Marina Ave approved?
Appealed to the Toronto Local Appeal Body. Source: Committee of Adjustment Applications, as of Nov 13, 2026.
Who is the councillor for 5 Marina Ave?
Amber Morley, Ward 3 Etobicoke-Lakeshore. Source: City Wards and Councillors, as of Nov 13, 2026.
Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.