Planning application · Site plan · Decided

Two towers, up to 43 storeys

50 St Lawrence Ave and 2 more addresses · Etobicoke City Centre · Ward 3 Etobicoke-Lakeshore

A request to approve the detailed design of two buildings of 43 and 34 storeys, with 289 homes. It was submitted in October 2023. It was refused.

City file 23 218177 WET 03 SA · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedOct 24, 2023
  2. DecisionRefused

01Outcome

DecidedRefused

This application is decided, so no more comments are taken on it.

The City’s data shows the decision but not its date.

02What was proposed

Two towers with 289 homes.

10 storeys20 storeys30 storeys40 storeys50 storeys4334TWO PROPOSED BUILDINGS
Heights in storeys, from the application.
Homes
289
Heights
43 and 34 storeys
Total floor space
18,006 m²
What it needed
Site plan approval (the City’s review of the detailed design)
The applicant’s description
The application is being submitted in two phases. Phase One being the two easterly towers at 34 and 43 storeys respectively, and Phase Two being the westerly 26 storey tower fronting onto the park.There are 289 units being proposed in Tower C (Phase Two) with 233 vehicular parking spaces and 348 bicycle parking spaces being proposed. The total gross floor area proposed is for Phase Two is 18,006 square metres, for a floor space index (FSI) of 2.19 times the site area. The total units for both Phase One and Phase Two (Site Plan Application 23 218177 WET 03 SA) being proposed are 1,166 units, with 485 total vehicular parking spaces and 904 total bicycle parking spaces, resulting in a total site density of 8.83 times the area of the lot.There is an active Official Plan Amendment and Zoning By-law Amendment application for the site (14 241637 WET05 OZ
From the City’s development applications data, as written.

03Timeline

  1. Oct 24, 2023Application submitted to the City.
  2. Oct 24, 2023A related site plan application is filed: Two towers, up to 43 storeys.
  3. —Refused. Date not in the City’s data.

04City files and documents

TypeFileStatus
Site planFile 23 218177 WET 03 SARefusedDocuments and reports on the City’s site
RezoningFile 14 241637 WET 03 OZUnder appealSee its page
Site planFile 23 218161 WET 03 SARefusedSee its page

Plans, studies and staff reports and the decision are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

F G Gardiner CF G Gardiner XyZorra StDorchester AveSt Lawrence AveArnold StOxford St123456Map data: City of Toronto (Toronto Centreline)F G Gardiner CZorra StSt Lawrence AveDorchester AveArnold StOxford St123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    43-storey building (1,166 homes)
    50 St Lawrence Ave · next door

    Appealed to the Ontario Land Tribunal

  2. 2
    12-storey building (321 homes)
    1045 The Queensway · about 140 m

    City planners are reviewing it

  3. 3
    Two towers, up to 43 storeys (495 homes)
    50 St Lawrence Ave · next door

    Refused

  4. 4
    12-storey building (321 homes)
    1045 The Queensway · about 140 m

    Approved by City Council

  5. 5
    Subdivision (4,222 homes)
    1025 The Queensway · about 290 m

    Draft plan approved

  6. 6
    Rezoning (4,078 homes)
    1025 The Queensway · about 290 m

    Approved by City Council

All applications in progress in Ward 3

06Quick answers about this application

What is proposed at 50 St Lawrence Ave?

Two towers with 289 homes, of 43 and 34 storeys, under City file 23 218177 WET 03 SA. Source: Development Applications, as of Nov 13, 2026.

Was the 50 St Lawrence Ave development approved?

No. Refused. Source: Development Applications, as of Nov 13, 2026.

Who is the councillor for 50 St Lawrence Ave?

Amber Morley, Ward 3 Etobicoke-Lakeshore. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

50 St Lawrence Ave development: Two towers, up to 43 storeys (refused) · My Address in Toronto