Planning application · Official Plan and rezoning · Decided

64-storey building

505 University Ave · Yonge-Bay Corridor · Ward 11 University-Rosedale

A request to change the Official Plan and zoning to allow a 64-storey building, with 704 homes. It was submitted in February 2024. The Ontario Land Tribunal approved it.

City file 24 118172 STE 11 OZ · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedFeb 23, 2024
  2. DecisionApproved by the Ontario Land Tribunal
  3. ThenSite plan and building permit

01Outcome

DecidedApproved by the Ontario Land Tribunal

This application is decided, so no more comments are taken on it.

What happens next: Before construction can start, the building needs site plan approval and a building permit. Neither has been filed in the City’s data yet. When they are, they’re added to the process bar above, the timeline and City files and documents.

The City’s data shows the decision but not its date.

02What was proposed

One 64-storey building with 704 homes.

20 storeys40 storeys60 storeys64PROPOSED
Heights in storeys, from the application.
Homes
704
Height
64 storeys
What it needed
Changes to the Official Plan and zoning (rules for what can be built where)
The applicant’s description
Official Plan Amendment application to permit a 64-storey mixed-use building, containing 704 dwelling units, 25,100 square metres of office and 600 square metres of retail gross floor area. A concurrent Zoning Amendment application for the same development has also previously been submitted and is under Appeal.
From the City’s development applications data, as written.

03Timeline

  1. Feb 23, 2024Application submitted to the City.
  2. —Approved by the Ontario Land Tribunal. Date not in the City’s data.

04City files and documents

TypeFileStatus
Official Plan and rezoningFile 24 118172 STE 11 OZApprovedDocuments and reports on the City’s site
Site planFile 22 198151 STE 11 SAIn progressSee its page

Plans, studies and staff reports and the decision are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

Dundas StBay StUniversity AveElm StMcCaul StSt Patrick StGrange RdHagerman StMichael Sweet AveSimcoe StEdward StChestnut StCentre AveElizabeth StArmoury St123456Map data: City of Toronto (Toronto Centreline)Dundas StUniversity AveElm StSt Patrick StMcCaul StSimcoe StMichael Sweet AveEdward StChestnut StElizabeth StArmoury StCentre Ave123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    64-storey building (704 homes)
    505 University Ave · next door

    City planners are reviewing it

  2. 2
    Two towers, up to 72 storeys with shops
    123 Edward St · about 100 m

    City planners are reviewing it

  3. 3
    64-storey building with shops (579 homes)
    522 University Ave · about 110 m

    City planners are reviewing it

  4. 4
    41-storey building with shops (135 homes)
    191 Dundas St W · about 140 m

    City planners are reviewing it

  5. 5
    Subdivision
    250 Dundas St W · about 190 m

    City planners are reviewing it

  6. 6
    Split the lot
    123 Edward St · about 220 m

    Hearing scheduled: hearing Sat, Oct 2

All applications in progress in Ward 11

06Quick answers about this application

What is proposed at 505 University Ave?

One 64-storey building with 704 homes, 64 storeys, under City file 24 118172 STE 11 OZ. Source: Development Applications, as of Nov 13, 2026.

Was the 505 University Ave development approved?

Yes. Approved by the Ontario Land Tribunal. Source: Development Applications, as of Nov 13, 2026.

When will it be built?

No date yet. It still needs site plan approval and a building permit, and none had been issued as of Nov 13, 2026. Source: Development Applications and Building Permits.

Who is the councillor for 505 University Ave?

Dianne Saxe, Ward 11 University-Rosedale. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

505 University Ave development: 64-storey building (approved by the ontario land tribunal) · My Address in Toronto