58-storey building

561 Jarvis St and 10 more addresses · North St.James Town · Ward 13 Toronto Centre

A request to approve the detailed design of a 58-storey building, with 818 homes. It was submitted in August 2022 and has been appealed to the Ontario Land Tribunal, which will make the final decision.

City file 22 185924 STE 13 SA · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedAug 4, 2022
  2. NowAppealed to the Ontario Land Tribunal
  3. NextTribunal hearing and decision

01Have your say

Nothing scheduled right now

Because the application has been appealed, the Ontario Land Tribunal, not City Council, will make the decision. No public meeting or comment deadline is set at the moment.

Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Chris Moise, can tell you how the City is handling the appeal.

02What’s proposed

One 58-storey building with 818 homes, on the site of the 3-storey rental building at 561 Jarvis St.

20 storeys40 storeys60 storeys583PROPOSEDON THE SITE TODAY
Heights in storeys, from the application. The existing building is from City records.
Homes
818
Height
58 storeys
What it needs
Site plan approval (the City’s review of the detailed design)
The applicant’s description
Site Plan Control application for a 58-storey residential building containing 818 dwelling units (including 31 rental replacement units) and 96.8 square metres of retail space on the ground floor.
From the City’s development applications data, as written.

03Timeline

  1. Aug 4, 2022Application submitted to the City.
  2. Aug 4, 2022A related rezoning application is filed: 58-storey building.
  3. —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.

04City files and documents

TypeFileStatus
Site planFile 22 185924 STE 13 SAUnder appealDocuments and reports on the City’s site
RezoningFile 22 185925 STE 13 OZUnder appealSee its page

Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

Church StWellesley StJarvis StSherbourne StDundonald StMaitland StMonteith StIsabella StGloucester StHomewood AveEarl PlCawthra SqLourdes LaneWellesley Pl123456Map data: City of Toronto (Toronto Centreline)Church StWellesley StJarvis StMaitland StMonteith StIsabella StMutual StEarl PlHuntley StCawthra SqGloucester StHomewood Ave123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    58-storey building (818 homes)
    102 Earl Pl · next door

    Appealed to the Ontario Land Tribunal

  2. 2
    29-storey building (335 homes)
    10 Huntley St · about 50 m

    Appealed to the Ontario Land Tribunal

  3. 3
    29-storey building
    10 Huntley St · about 50 m

    City planners are reviewing it

  4. 4
    63-storey building
    2 Earl St · about 80 m

    City planners are reviewing it

  5. 5
    69-storey building (770 homes)
    135 Isabella St · about 140 m

    City planners are reviewing it

  6. 6
    Two towers, up to 60 storeys (1,362 homes)
    30 Huntley St · about 140 m

    City planners are reviewing it

All applications in progress in Ward 13

06Quick answers about this application

What is proposed at 561 Jarvis St?

One 58-storey building with 818 homes, 58 storeys, under City file 22 185924 STE 13 SA. Source: Development Applications, as of Nov 13, 2026.

Has the 561 Jarvis St development been approved?

Not yet. It has been appealed to the Ontario Land Tribunal, which will make the final decision. Source: Development Applications, as of Nov 13, 2026.

Can I comment on it?

No meeting or comment deadline is scheduled right now. Follow the application to get an email if one is set. Source: Development Applications and Public Notices, as of Nov 13, 2026.

Who is the councillor for 561 Jarvis St?

Chris Moise, Ward 13 Toronto Centre. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

561 Jarvis St development: 58-storey building (under appeal) · My Address in Toronto