Skip to content
My Address in Toronto
Planning application · Committee of Adjustment · Consent · Decided

Split the lot

66 Brookfield St · Trinity-Bellwoods · Ward 10 Spadina-Fort York

The owner is asking for permission to divide the property or change its lot lines to obtain consent to sever a portion of land for the purpose of a lot addition. The Committee of Adjustment decided: approved.

City file B0060/24TEY · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedJul 31, 2024
  2. HearingFeb 26, 2025
  3. DecisionApproved
  4. ThenBuilding permit

01Outcome

DecidedApproved by the Committee of Adjustment

This application is decided, so no more comments are taken on it.

The decision can be appealed to the Toronto Local Appeal Body until Mar 24, 2025.

What happens next: The owner can now apply for a building permit. When one is issued, it’s added to the timeline below.

02What was proposed

To obtain consent to sever a portion of land for the purpose of a lot addition.

The application’s description, from the City’s Committee of Adjustment data. A consent is permission to divide a property or change its lot lines.

03Timeline

  1. Jul 31, 2024Application submitted to the City.
  2. Feb 26, 2025Committee of Adjustment hearing: approved.
  3. —Approved by the Committee of Adjustment. Date not in the City’s data.

04City files and documents

TypeFileStatus
ConsentFile B0060/24TEYApprovedThe City’s Application Information Centre

Plans, studies and staff reports and the decision are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

Ossington AveQueen StFennings StHumbert StDovercourt RdArgyle StAfton AveLisgar StFoxley StBrookfield StBeaconsfield AveGivins StShaw StLobb AveRebecca St123456Map data: City of Toronto (Toronto Centreline)Queen StOssington AveGrove AveFennings StDovercourt RdArgyle StFoxley StBrookfield StLisgar StGivins StRebecca StHumbert St123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    10-storey building (74 homes)
    1113 Dundas St W · about 210 m

    City planners are reviewing it

  2. 2
    Add a storey
    16 Skey Lane · about 300 m

    Hearing scheduled: hearing Wed, Dec 2

  3. 3
    3-storey building (4 homes)
    26 Ossington Ave · about 330 m

    City planners are reviewing it

  4. 4
    New three-storey house
    34 Grove Ave · about 370 m

    Appealed to the Toronto Local Appeal Body

  5. 5
    Second suite
    1136 Queen St W · about 370 m

    Waiting for a hearing date

  6. 6
    Add a storey
    1161 Dundas St W · about 400 m

    Appealed to the Toronto Local Appeal Body

All applications in progress in Ward 10

06Quick answers about this application

What is being built at 66 Brookfield St?

To obtain consent to sever a portion of land for the purpose of a lot (file B0060/24TEY). Source: Committee of Adjustment Applications, as of Nov 13, 2026.

Was the application at 66 Brookfield St approved?

Approved by the Committee of Adjustment. Source: Committee of Adjustment Applications, as of Nov 13, 2026.

Who is the councillor for 66 Brookfield St?

Ausma Malik, Ward 10 Spadina-Fort York. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

66 Brookfield St Committee of Adjustment: Split the lot (approved) · My Address in Toronto