Skip to content
My Address in Toronto
Planning application · Rezoning

43-storey building

69 Ontario St and 5 more addresses · Moss Park · Ward 13 Toronto Centre

A request to change the zoning to allow a 43-storey building, with 380 homes. It was submitted in December 2019 and has been appealed to the Ontario Land Tribunal, which will make the final decision.

City file 19 265929 STE 13 OZ · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedDec 31, 2019
  2. Community meetingDec 14, 2020
  3. NowAppealed to the Ontario Land Tribunal
  4. NextTribunal hearing and decision

01Have your say

Nothing scheduled right now

Because the application has been appealed, the Ontario Land Tribunal, not City Council, will make the decision. No public meeting or comment deadline is set at the moment.

Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Chris Moise, can tell you how the City is handling the appeal.

02What’s proposed

One 43-storey building with 380 homes.

10 storeys20 storeys30 storeys40 storeys50 storeys43PROPOSED
Heights in storeys, from the application.
Homes
380
Height
43 storeys
Total floor space
23,139 m²
What it needs
A change to the zoning (rules for what can be built where)
The applicant’s description
Zoning By-law Amendment application to permit a 43-storey mixed-use building that includes 278 square metres of retail space on the ground floor and 380 dwelling units above.
From the City’s development applications data, as written.

03Timeline

  1. Dec 31, 2019Application submitted to the City.
  2. Dec 14, 2020Community consultation meeting.
  3. Nov 8, 2021A related condominium application is filed: 38-storey building.
  4. Aug 11, 2023A related site plan application is filed: 43-storey building.
  5. —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.

04City files and documents

TypeFileStatus
RezoningFile 19 265929 STE 13 OZUnder appealDocuments and reports on the City’s site
CondominiumFile 21 235323 STE 13 CDIn progressSee its page
Site planFile 23 187639 STE 13 SAUnder appealSee its page

Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

Adelaide StKing StParliament StSherbourne StRichmond StFront StJarvis StLower Sherbourne StBritain StTrinity StPrincess StBerkeley StErin StOntario StDerby StFrederick StHahn Pl123456Map data: City of Toronto (Toronto Centreline)Richmond StKing StSherbourne StFront StAdelaide StLower Sherbourne StPrincess StBerkeley StOntario StFrederick St123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    38-storey building (354 homes)
    69 Ontario St · next door

    City planners are reviewing it

  2. 2
    43-storey building (380 homes)
    69 Ontario St · next door

    Appealed to the Ontario Land Tribunal

  3. 3
    181 homes
    102 Berkeley St · about 60 m

    City planners are reviewing it

  4. 4
    35-storey building (257 homes)
    102 Berkeley St · about 60 m

    City planners are reviewing it

  5. 5
    Site plan (588 homes)
    494 Richmond St E · about 130 m

    City planners are reviewing it

  6. 6
    25-storey building (446 homes)
    348 Richmond St E · about 170 m

    City planners are reviewing it

All applications in progress in Ward 13

06Quick answers about this application

What is proposed at 69 Ontario St?

One 43-storey building with 380 homes, 43 storeys, under City file 19 265929 STE 13 OZ. Source: Development Applications, as of Nov 13, 2026.

Has the 69 Ontario St development been approved?

Not yet. It has been appealed to the Ontario Land Tribunal, which will make the final decision. Source: Development Applications, as of Nov 13, 2026.

Can I comment on it?

No meeting or comment deadline is scheduled right now. Follow the application to get an email if one is set. Source: Development Applications and Public Notices, as of Nov 13, 2026.

Who is the councillor for 69 Ontario St?

Chris Moise, Ward 13 Toronto Centre. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

69 Ontario St development: 43-storey building (under appeal) · My Address in Toronto