Skip to content
My Address in Toronto
Planning application · Committee of Adjustment · Minor variance

Addition

91 Lake Promenade · Long Branch · Ward 3 Etobicoke-Lakeshore

The owner is asking for exceptions to the zoning rules to construct a two-storey front addition and a new rear deck. The decision has been appealed.

City file A0526/21EYK · Data as of Nov 13, 2026 · Every item lists its source

Where it is in the process
  1. SubmittedOct 16, 2021
  2. HearingNov 30, 2021
  3. DecisionRefused by the Committee
  4. NowAppealed to the Toronto Local Appeal Body
  5. NextAppeal hearing and decision

01Have your say

Nothing scheduled right now

Because the application has been appealed, the Toronto Local Appeal Body, not the Committee of Adjustment, will make the decision. No public meeting or comment deadline is set at the moment.

Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Amber Morley, can tell you how the City is handling the appeal.

02What’s proposed

To construct a two-storey front addition and a new rear deck.

The application’s description, from the City’s Committee of Adjustment data. A minor variance is permission for a small exception to the zoning rules, such as height or lot coverage.

03Timeline

  1. Oct 16, 2021Application submitted to the City.
  2. Nov 30, 2021Committee of Adjustment hearing: refused.
  3. —Appealed to the Toronto Local Appeal Body. Date not published in the City’s data; from now on we record the date we first see each change.

04City files and documents

TypeFileStatus
Minor varianceFile A0526/21EYKUnder appealThe City’s Application Information Centre

Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.

05Nearby applications

Arcadian CrclThirty First StCrystal CresLake PromenadeJasmine AveElton CresTwenty Fifth StTwenty Third St123456Map data: City of Toronto (Toronto Centreline)Twenty Seventh StLake PromenadeTwenty Eighth StJasmine AveArcadian CrclTwenty Fifth St123456Map data: City of Toronto (Toronto Centreline)

The red dot is this application. The circle shows 400 metres, about a 5-minute walk.

  1. 1
    New house
    106 Lake Promenade · about 90 m

    Appealed to the Toronto Local Appeal Body

  2. 2
    Minor variance
    50 Lake Promenade · about 160 m

    Waiting for a hearing date

  3. 3
    New house
    29 Lake Promenade · about 250 m

    Appealed to the Toronto Local Appeal Body

  4. 4
    Split the lot
    15 Ramsgate Rd · about 300 m

    Appealed to the Toronto Local Appeal Body

  5. 5
    Site plan
    45 Twenty Third St · about 310 m

    City planners are reviewing it

  6. 6
    Split the lot
    10 Lake Promenade · about 310 m

    Appealed to the Toronto Local Appeal Body

All applications in progress in Ward 3

06Quick answers about this application

What is being built at 91 Lake Promenade?

To construct a two-storey front addition and a new rear (file A0526/21EYK). Source: Committee of Adjustment Applications, as of Nov 13, 2026.

Was the application at 91 Lake Promenade approved?

Appealed to the Toronto Local Appeal Body. Source: Committee of Adjustment Applications, as of Nov 13, 2026.

Who is the councillor for 91 Lake Promenade?

Amber Morley, Ward 3 Etobicoke-Lakeshore. Source: City Wards and Councillors, as of Nov 13, 2026.

Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.

91 Lake Promenade Committee of Adjustment: Addition · My Address in Toronto