Rezoning
680 Progress Ave and 2 more addresses · Woburn North · Ward 24 Scarborough-Guildwood
A request to change the Official Plan and zoning for 680 Progress Ave. It was submitted in December 2019 and has been appealed to the Ontario Land Tribunal, which will make the final decision.
City file 19 257336 ESC 24 OZ · Data as of Nov 13, 2026 · Every item lists its source
- SubmittedDec 4, 2019
- Community meetingApr 16, 2018
- NowAppealed to the Ontario Land Tribunal
- NextTribunal hearing and decision
01Have your say
Because the application has been appealed, the Ontario Land Tribunal, not City Council, will make the decision. No public meeting or comment deadline is set at the moment.
Follow this application and we’ll email you if a hearing is scheduled. Your councillor, Paul Ainslie, can tell you how the City is handling the appeal.
02What’s proposed
The applicant’s description
Official Plan Amendment application to establish a site-specific parkland dedication rate for the subject lands, which are within Scarborough Centre. The application is to be reviewed concurrently with the related Rezoning application for a mixed use development (File #: 17 277456 ESC 38 OZ) and Draft Plan of Subdivision application (File #: 17 277479 ESC 38 OZ).From the City’s development applications data, as written.
03Timeline
- Apr 16, 2018Community consultation meeting.
- Dec 4, 2019Application submitted to the City.
- Dec 31, 2021A related site plan application is filed: 40-storey building.
- —Appealed to the Ontario Land Tribunal. Date not published in the City’s data; from now on we record the date we first see each change.
04City files and documents
| Type | File | Status | |
|---|---|---|---|
| Official Plan and rezoning | File 19 257336 ESC 24 OZ | Under appeal | Documents and reports on the City’s site |
| Subdivision | File 17 277479 ESC 38 SB | In progress | See its page |
| Site plan | File 21 252432 ESC 24 SA | In progress | See its page |
Plans, studies and staff reports are on the City’s Application Information Centre. We link to them rather than copy them.
05Nearby applications
The red dot is this application. The circle shows 400 metres, about a 5-minute walk.
- 1
- 2
- 3Two towers, up to 46 storeys (935 homes)710 Progress Ave · about 170 m
City planners are reviewing it
- 4
- 5
- 6
06Quick answers about this application
What is proposed at 680 Progress Ave?
Rezoning, under City file 19 257336 ESC 24 OZ. Source: Development Applications, as of Nov 13, 2026.
Has the 680 Progress Ave development been approved?
Not yet. It has been appealed to the Ontario Land Tribunal, which will make the final decision. Source: Development Applications, as of Nov 13, 2026.
Can I comment on it?
No meeting or comment deadline is scheduled right now. Follow the application to get an email if one is set. Source: Development Applications and Public Notices, as of Nov 13, 2026.
Who is the councillor for 680 Progress Ave?
Paul Ainslie, Ward 24 Scarborough-Guildwood. Source: City Wards and Councillors, as of Nov 13, 2026.
Sources: City of Toronto Development Applications, Committee of Adjustment Applications, Public Notices and Building Permits (Open Data, updated nightly). Not legal advice. Something wrong? Tell us.